Buy/Sell PTO Plan Setup

📘

Buy/Sell PTO Plan

This plan allows for the buying and/or selling of Paid Time Off (PTO) in full or partial increments of hours, days, weeks, or months. With this update, a step-by-step guide on Best Practices for setting up this plan for use in bCEnroll is available below.

592

Initial Setup Workflow – Average Compensation

The following is the best practice for creating a new Buy/Sell PTO benefit plan in bC4 for use in bCEnroll.

  1. Login to bC4.
  2. Search for and select your Company.
  3. Click Company Administration and select Company Information.
  4. Click the Benefits tab and select Buy/Sell PTO.
  5. Click Add New
  6. Complete the General Plan Design as you would any other plan and click Next.

7. Cost & Coverages:

884

Words

  •      a.	PTO Units are Based On – This is the increment in which the employee is allowed to Buy/Sell their PTO. If this is set to 2 Hours then an employee can buy or sell 2 hours at a time. The dropdown can be set to Hours, Days, Weeks, or Months. 
    
  •      b.	PTO Units Per Year – How many PTO Hours/Days/Weeks/Months total are available to an employee each year?  *This will auto-populate with the total amount an employee is expected to work in a year and should be changed to how much PTO is available to that employee.* 
    
431

For example, if the PTO Units are Based On is set to “Hours” then this field will populate with 2080 which is how many hours an employee would work if they worked every week day for one year.

  • c. PTO Units Allowed To Buy – How many PTO Hours/Days/Weeks/Months are available for an employee to BUY each year? This number should be able to be evenly divided by the number entered in the PTO Units are Based on field. For example, if the PTO Units are Based On has 2 (as in the example above) then this field should only contain even numbers that can be divided by 2.
  • d. PTO Units Allowed To Sell – How many PTO Hours/Days/Weeks/Months are available for an employee to SELL each year? This number should be able to be evenly divided by the number entered in the PTO Units are Based on field. For example, if the PTO Units are Based On has 2 (as in the example above) then this field should only contain numbers that can be divided by 2.
  • e. Determine PTO Unit Cost/Credit By – This should be set to “Average Compensation per PTO Unit” meaning it will determine the what an employee would make in a given hour/day/week/month (pending which unit was initially selected) and determine the cost or credit based on how much the employee would have made had they been working instead of using their PTO.
598
  • f. Per-unit Cost/Credit Amount – When using “Average Compensation per PTO Unit” this field should be left blank as it will have no bearing on the cost.
  • g. Basis for Compensation Average – This field should reflect the average expected hours an employee would work in any given week in order to calculate an expectation of how much an employee would have made had they worked instead of used their PTO. For Full Time employees, this number is most commonly 40 hours.
  • h. Round PTO Costs – For use in bCEnroll, this should always be set to “Nearest Penny”
  • i. Compensation Basis Flag – Select what time of year should be used for an employee’s compensation.
  • j. Include Additional Compensation Factors – This should currently be left blank.
  • k. Prorate Allowed Contributions – This should be set to “No”.
  • l. Click Next and proceed as you would with any other benefit plan.
595

📘

Now that we have reviewed how to setup a Buy/Sell PTO plan with the cost based on Average Compensation, the following is how to setup the plan with the cost determined by a Flat Amount.

Initial Setup Workflow – Flat Amount

The following is the best practice for creating a new Buy/Sell PTO benefit plan in bC4 for use in bCEnroll.

  1. Login to bC4.
  2. Search for and select your Company.
  3. Click Company Administration and select Company Information.
  4. Click the Benefits tab and select Buy/Sell PTO.
  5. Click Add New
  6. Complete the General Plan Design as you would any other plan and click Next.

7. Cost & Coverages:

891
  •      a.	PTO Units are Based On – This is the increment in which the employee is allowed to Buy/Sell their PTO. If this is set to 2 Hours then an employee can buy or sell 2 hours at a time. The dropdown can be set to Hours, Days, Weeks, or Months. 
    
  •      b.	PTO Units Per Year – How many PTO Hours/Days/Weeks/Months total are available to an employee each year?  *This will auto-populate with the total amount an employee is expected to work in a year and should be changed to how much PTO is available to that employee.* 
    
431

For example, if the PTO Units are Based On is set to “Hours” then this field will populate with 2080 which is how many hours an employee would work if they worked every week day for one year.

  • c. PTO Units Allowed To Buy – How many PTO Hours/Days/Weeks/Months are available for an employee to BUY each year? This number should be able to be evenly divided by the number entered in the PTO Units are Based on field. For example, if the PTO Units are Based On has 2 (as in the example above) then this field should only contain even numbers that can be divided by 2.
  • d. PTO Units Allowed To Sell – How many PTO Hours/Days/Weeks/Months are available for an employee to SELL each year? This number should be able to be evenly divided by the number entered in the PTO Units are Based on field. For example, if the PTO Units are Based On has 2 (as in the example above) then this field should only contain numbers that can be divided by 2.
  • e. Determine PTO Unit Cost/Credit By – This should be set to “Flat Amount Cost [Enter Below]” meaning the cost or credit will be determined based on what is entered in the Per-unit Cost/Credit Amount field.
590
  • f. Per-unit Cost/Credit Amount – This number should reflect the ANNUAL cost for a single unit. If an employee on a bi-weekly payroll schedule is selling hours and each hour costs $10 per-pay-period, the annual cost would be $260.
  • g. Basis for Compensation Average – To calculate an expectation of how much an employee would have made had they worked instead of used PTO, this field should reflect the average expected hours an employee would work in any given week. For Full Time employees, this number is most commonly 40 hours.
  • h. Round PTO Costs – For use in bCEnroll, this should always be set to “Nearest Penny”.
  • i. Compensation Basis Flag – When using “Flat Amount” this field will have no bearing on the cost.
  • j. Include Additional Compensation Factors – This should currently be left blank.
  • k. Prorate Allowed Contributions – This should be set to “No”.
  • l. Click Next and proceed as you would with any other benefit plan.
598